ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0258 · BESS · Dallas County

watermelon 8 energy storage

watermelon 8 energy storage is a 102 MW battery storage project in Dallas County, Texas, connecting at Tap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0258
Capacity
102 MW
Fuel
BESS (BA)
Interconnecting entity
Tempus power management LLC
Projected COD
03/01/2029
Entered queue
02/06/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/06/2025
    Entered the queue with 102 MW, projected COD 03/01/2029
  • 02/06/2025
    Screening → FIS Requested

Other projects at this substation

watermelon 1 energy storageBESS102 MWFIS Requested
watermelon 2 energy storageBESS102 MWFIS Requested
watermelon 4 energy storageBESS102 MWFIS Requested
watermelon 5 energy storageBESS102 MWFIS Requested
watermelon 6 energy storageBESS102 MWFIS Requested
watermelon 7 energy storageBESS102 MWFIS Requested