28INR0253 · BESS · Stonewall County
Stonewall BESS
Stonewall BESS is a 135 MW battery storage project in Stonewall County, Texas, connecting at tap 138kV 6150 SPUR4A - 6158 ASPM4A. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/29/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0253
- Capacity
- 135 MW
- Fuel
- BESS (BA)
- Substation
- tap 138kV 6150 SPUR4A - 6158 ASPM4A
- County
- Stonewall County
- Interconnecting entity
- Stonewall ESS, LLC
- Projected COD
- 12/29/2028
- Entered queue
- 02/06/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/06/2025Entered the queue with 135 MW, projected COD 12/29/2028
- 02/06/2025Screening → FIS Requested