ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0230 · BESS · Duval County

Allthorn BESS

Allthorn BESS is a 205 MW battery storage project in Duval County, Texas, connecting at Tap 138 kV BRUNI44A (#8297) - CRESTONI4A (#8695). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/15/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0230
Capacity
205 MW
Fuel
BESS (BA)
Interconnecting entity
ALLTHORN SOLAR, LLC
Projected COD
01/15/2029
Entered queue
02/03/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/03/2025
    Entered the queue with 205 MW, projected COD 01/15/2029
  • 02/03/2025
    Screening → FIS Requested