Saddlehorn Energy Storage

Saddlehorn Energy Storage is a 257 MW battery storage project in Austin County, Texas, connecting at Tap 138kV 7287 Bellville North - 7291 Highway 36. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 11/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0186
Capacity
257 MW
Fuel
BESS (BA)
Interconnecting entity
Saddlehorn Energy Storage, LLC
Projected COD
11/01/2028
Entered queue
11/26/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/03/2024
    Screening → FIS Requested
  • 11/26/2024
    Entered the queue with 257 MW, projected COD 11/01/2028