28INR0180 · Solar · Kenedy County

Green Ocelot Solar

Green Ocelot Solar is a 357 MW solar project in Kenedy County, Texas, connecting at Tap 345kV 80076 Ajo - 8601 Cebolla. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 11/17/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0180
Capacity
357 MW
Fuel
Solar (PV)
Interconnecting entity
Ocelot Solar LLC
Projected COD
11/17/2028
Entered queue
01/28/2025
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/29/2026
    FIS Requested → FIS Approved
  • 01/28/2025
    Entered the queue with 357 MW, projected COD 11/17/2028
  • 01/28/2025
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.