28INR0157 · BESS · Mclennan County
Axtell BESS
Axtell BESS is a 307 MW battery storage project in Mclennan County, Texas, connecting at 345 kV Tiger Creek Switch (#3379). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/16/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0157
- Capacity
- 307 MW
- Fuel
- BESS (BA)
- Substation
- 345 kV Tiger Creek Switch (#3379)
- County
- Mclennan County
- Interconnecting entity
- PP Axtell BESS LLC
- Projected COD
- 04/16/2029
- Entered queue
- 10/01/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/01/2026Screening → FIS Requested
- 10/01/2024Entered the queue with 307 MW, projected COD 04/16/2029
Other projects at this substation
No other projects at this substation.