LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0151 · Solar · Shackelford County

Chimney Creek Solar

Chimney Creek Solar is a 204 MW solar project in Shackelford County, Texas, connecting at Tap 345 kV 68000 West Shackelford – 60515 Clear Crossing Ckt 1. ERCOT's October 2026 report shows it at the Screening stage with a projected commercial operation date of 05/30/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0151
Capacity
204 MW
Fuel
Solar (PV)
Interconnecting entity
Chimney Creek Energy, LLC
Projected COD
05/30/2030
Entered queue
02/14/2025
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/14/2025
    Entered the queue with 204 MW, projected COD 05/30/2030

Other projects at this substation

No other projects at this substation.