28INR0119 · BESS · Mitchell County

Rabbit Hollow Energy Storage

Rabbit Hollow Energy Storage is a 342 MW battery storage project in Mitchell County, Texas, connecting at 1190 Barber Lake Switch 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0119
Capacity
342 MW
Fuel
BESS (BA)
Interconnecting entity
Rabbit Hollow Energy Storage, LLC
Projected COD
12/31/2029
Entered queue
12/01/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/01/2024
    Entered the queue with 342 MW, projected COD 12/31/2029
  • 12/01/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.