28INR0094 · BESS · Anderson County
Pham BESS
Pham BESS is a 133 MW battery storage project in Anderson County, Texas, connecting at Tap 138kV 3281 TENNCLNY_8 - 3499 BLACKFTAP_8. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/18/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0094
- Capacity
- 133 MW
- Fuel
- BESS (BA)
- County
- Anderson County
- Interconnecting entity
- ASB1, LLC
- Projected COD
- 09/18/2028
- Entered queue
- 06/13/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/31/2026Screening → IA Signed
- 06/13/2024Entered the queue with 133 MW, projected COD 09/18/2028
Other projects at this substation
No other projects at this substation.