LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0094 · BESS · Anderson County

Pham BESS

Pham BESS is a 133 MW battery storage project in Anderson County, Texas, connecting at Tap 138kV 3281 TENNCLNY_8 - 3499 BLACKFTAP_8. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/18/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0094
Capacity
133 MW
Fuel
BESS (BA)
Interconnecting entity
ASB1, LLC
Projected COD
09/18/2028
Entered queue
06/13/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/31/2026
    Screening → IA Signed
  • 06/13/2024
    Entered the queue with 133 MW, projected COD 09/18/2028

Other projects at this substation

No other projects at this substation.