28INR0073 · Solar · Karnes County
Daystar Solar
Daystar Solar is a 150 MW solar project in Karnes County, Texas, connecting at 5728 Choate 138kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 09/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0073
- Capacity
- 150 MW
- Fuel
- Solar (PV)
- Substation
- 5728 Choate 138kV
- County
- Karnes County
- Interconnecting entity
- Choate Solar, LLC
- Projected COD
- 09/15/2028
- Entered queue
- 04/09/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/13/2026FIS Requested → FIS Approved
- 04/09/2024Entered the queue with 150 MW, projected COD 09/15/2028
- 04/09/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.