27INR0625 · BESS · Swisher County
Hornet Energy Storage SLF
COD delayed 1×
Hornet Energy Storage SLF is a 0 MW battery storage project in Swisher County, Texas, connecting at 23901 OZARKTRAIL_5 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/30/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0625
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 23901 OZARKTRAIL_5 345kV
- County
- Swisher County
- Interconnecting entity
- Hornet Energy Storage LLC
- Projected COD
- 09/30/2029
- Entered queue
- 04/09/2026
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 09/30/2028 → 09/30/2029 (+12 months)
- 04/09/2026Entered the queue with 0 MW, projected COD 09/30/2028
- 04/09/2026Screening → FIS Requested
Other projects at this substation