27INR0619 · BESS · Wise County
Prairie Point Energy Storage II
Prairie Point Energy Storage II is a 1,000 MW battery storage project in Wise County, Texas, connecting at RAMHORNH 5 - 31875. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0619
- Capacity
- 1,000 MW
- Fuel
- BESS (BA)
- Substation
- RAMHORNH 5 - 31875
- County
- Wise County
- Interconnecting entity
- Prairie Point LLC
- Projected COD
- 12/31/2027
- Entered queue
- 04/30/2026
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/30/2026Entered the queue with 1,000 MW, projected COD 12/31/2027
- 04/30/2026Screening → FIS Requested
Other projects at this substation
| Prairie Point Energy Storage I | BESS | 1,000 MW | FIS Requested |