27INR0524 · BESS · San Patricio County
Portland Storage SLF
Portland Storage SLF is a 0 MW battery storage project in San Patricio County, Texas, connecting at 8566 HOT IRON 4A 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/03/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0524
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- Substation
- 8566 HOT IRON 4A 138 kV
- County
- San Patricio County
- Interconnecting entity
- Convergent Energy Solutions LLC
- Projected COD
- 01/03/2028
- Entered queue
- 07/18/2025
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/18/2025Entered the queue with 0 MW, projected COD 01/03/2028
- 07/18/2025Screening → FIS Requested