27INR0498 · Gas · Mclennan County

Infrakey Waco Data Park Gas 2

Infrakey Waco Data Park Gas 2 is a 0 MW natural gas project in Mclennan County, Texas, connecting at 252 BOSQUESW8 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0498
Capacity
0 MW
Fuel
Gas (GT)
Interconnecting entity
Infrakey Capital LLC
Projected COD
06/01/2030
Entered queue
04/21/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/14/2026
    Screening → FIS Requested
  • 04/21/2025
    Entered the queue with 0 MW, projected COD 06/01/2030