27INR0486 · BESS · Travis County
Blackland Prairie 2 Energy Storage
COD delayed 1×
Blackland Prairie 2 Energy Storage is a 102 MW battery storage project in Travis County, Texas, connecting at 9328 Austrop 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2030. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0486
- Capacity
- 102 MW
- Fuel
- BESS (BA)
- Substation
- 9328 Austrop 138kV
- County
- Travis County
- Interconnecting entity
- Balcones Ridge Resiliency II LLC
- Projected COD
- 12/01/2030
- Entered queue
- 02/24/2025
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 12/01/2027 → 12/01/2030 (+36 months)
- 02/24/2025Entered the queue with 102 MW, projected COD 12/01/2027
- 02/24/2025Screening → FIS Requested
Other projects at this substation
| Blackland Prairie 1 Energy Storage | BESS | 102 MW | IA Signed |
| Blackland Prairie 3 Energy Storage | BESS | 102 MW | FIS Requested |