27INR0445 · Wind · Tom Green County
Moon Chapel Wind
Moon Chapel Wind is a 379 MW wind project in Tom Green County, Texas, connecting at Tap 345kV 76090 Divide - 76009 Twin Buttes Ckt 1. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0445
- Capacity
- 379 MW
- Fuel
- Wind (WT)
- County
- Tom Green County
- Interconnecting entity
- Orsted Onshore Development North America, LLC
- Projected COD
- 10/01/2028
- Entered queue
- 02/07/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 02/07/2025Entered the queue with 379 MW, projected COD 10/01/2028
- 02/07/2025Screening → FIS Requested
Other projects at this substation
| Moon Chapel Solar | Solar | 402 MW | Screening |