27INR0443 · Wind · Armstrong County
Serenity Wind
Serenity Wind is a 473 MW wind project in Armstrong County, Texas, connecting at 23931 MIDPOINT SWITCH 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/18/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0443
- Capacity
- 473 MW
- Fuel
- Wind (WT)
- Substation
- 23931 MIDPOINT SWITCH 345 kV
- County
- Armstrong County
- Interconnecting entity
- Serenity Wind, LLC
- Projected COD
- 09/18/2028
- Entered queue
- 03/07/2025
- ERCOT zone
- PANHANDLE
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/07/2025Entered the queue with 473 MW, projected COD 09/18/2028
- 03/07/2025Screening → FIS Requested
Other projects at this substation
No other projects at this substation.