27INR0400 · BESS · Brooks County
Reforzar BESS 1
Reforzar BESS 1 is a 208 MW battery storage project in Brooks County, Texas, connecting at 345 kV 80078 Reforzar. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/13/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0400
- Capacity
- 208 MW
- Fuel
- BESS (BA)
- Substation
- 345 kV 80078 Reforzar
- County
- Brooks County
- Interconnecting entity
- Tempus Power management LLC
- Projected COD
- 04/13/2028
- Entered queue
- 11/05/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 06/18/2026FIS Requested → FIS Approved
- 11/05/2024Entered the queue with 208 MW, projected COD 04/13/2028
- 11/05/2024Screening → FIS Requested
Other projects at this substation
| Reforzar Bess 2 | BESS | 208 MW | FIS Requested |