ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0399 · BESS · Cameron County

Resaca Oasis Storage

Resaca Oasis Storage is a 201 MW battery storage project in Cameron County, Texas, connecting at # 79601 Stillman Substation 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/20/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0399
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Resaca Oasis Storage, LLC
Projected COD
09/20/2028
Entered queue
11/22/2024
ERCOT zone
COASTAL
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/10/2025
    FIS Requested → FIS Approved
  • 05/22/2025
    FIS Approved → IA Signed
  • 11/22/2024
    Entered the queue with 201 MW, projected COD 09/20/2028
  • 11/22/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.