LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0354 · BESS · Smith County

Cebocell BESS

Cebocell BESS is a 201 MW battery storage project in Smith County, Texas, connecting at 3137 BlackFork 138 KV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 10/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0354
Capacity
201 MW
Fuel
BESS (BA)
Interconnecting entity
Cebocell, LLC
Projected COD
10/31/2028
Entered queue
08/13/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/13/2024
    Entered the queue with 201 MW, projected COD 10/31/2028
  • 08/13/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.