27INR0330 · Solar · Dimmit County
Wild Horse Desert Solar
Wild Horse Desert Solar is a 120 MW solar project in Dimmit County, Texas, connecting at Tap 138kV 8613 Big Well - 8212 Dilley Switch. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0330
- Capacity
- 120 MW
- Fuel
- Solar (PV)
- County
- Dimmit County
- Interconnecting entity
- Wild Horse Desert Solar, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 12/06/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 09/14/2026FIS Requested → FIS Approved
- 12/06/2024Entered the queue with 120 MW, projected COD 07/01/2028
- 12/06/2024Screening → FIS Requested
Other projects at this substation