27INR0317 · BESS · Van Zandt County

Edgewood BESS 1

Edgewood BESS 1 is a 102 MW battery storage project in Van Zandt County, Texas, connecting at Tap Edgewood 138kV bus(3181) to CANTNSW_8 (3174). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0317
Capacity
102 MW
Fuel
BESS (BA)
Interconnecting entity
Tempus Power management LLC
Projected COD
03/01/2028
Entered queue
11/05/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/05/2024
    Entered the queue with 102 MW, projected COD 03/01/2028
  • 11/05/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.