LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0316 · BESS · Freestone County

Avant Prairie BESS

Avant Prairie BESS is a 202 MW battery storage project in Freestone County, Texas, connecting at Tap 345kV BIGBRNE (#3380) - JEWETT (#3390) CKT 1. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/16/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0316
Capacity
202 MW
Fuel
BESS (BA)
Interconnecting entity
Avant Prairie ESS LLC
Projected COD
04/16/2029
Entered queue
09/02/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/01/2026
    FIS Requested → FIS Approved
  • 09/02/2024
    Entered the queue with 202 MW, projected COD 04/16/2029
  • 09/02/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.