27INR0261 · Solar · Schleicher County
Tipperary Solar
Tipperary Solar is a 60 MW solar project in Schleicher County, Texas, connecting at 6498 Live Oak AEP 69kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 03/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0261
- Capacity
- 60 MW
- Fuel
- Solar (PV)
- Substation
- 6498 Live Oak AEP 69kV
- County
- Schleicher County
- Interconnecting entity
- Tippsol
- Projected COD
- 03/15/2028
- Entered queue
- 05/17/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/17/2024Entered the queue with 60 MW, projected COD 03/15/2028
- 05/17/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.