LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0241 · Solar · Menard County

Callan Solar

COD delayed 1×

Callan Solar is a 91 MW solar project in Menard County, Texas, connecting at Tap 69kV 60386 Heartland to 6363 Yellow Jacket. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/30/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0241
Capacity
91 MW
Fuel
Solar (PV)
Interconnecting entity
Menard PV, LLC
Projected COD
12/30/2029
Entered queue
06/04/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 09/01/2028 → 12/30/2029 (+16 months)
  • 06/04/2024
    Entered the queue with 91 MW, projected COD 09/01/2028
  • 06/04/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.