27INR0231 · BESS · Schleicher County
Easy Battery Energy Storage Center
Easy Battery Energy Storage Center is a 200 MW battery storage project in Schleicher County, Texas, connecting at Tap 345 kV 76003 Big Hill to 76005 Schneeman Draw. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/15/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0231
- Capacity
- 200 MW
- Fuel
- BESS (BA)
- County
- Schleicher County
- Interconnecting entity
- Easy Wind Energy Center, LLC
- Projected COD
- 06/15/2029
- Entered queue
- 03/20/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/20/2024Entered the queue with 200 MW, projected COD 06/15/2029
- 03/20/2024Screening → FIS Requested