ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0198 · Solar · Henderson County

Musgravite Solar

Musgravite Solar is a 101 MW solar project in Henderson County, Texas, connecting at Tap 138 kV (6855) Coffee - (6849) New York.. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 11/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0198
Capacity
101 MW
Fuel
Solar (PV)
Interconnecting entity
Solex Ridge, LLC
Projected COD
11/01/2027
Entered queue
03/06/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/06/2025
    FIS Requested → FIS Approved
  • 05/20/2025
    FIS Approved → IA Signed
  • 03/06/2024
    Entered the queue with 101 MW, projected COD 11/01/2027
  • 03/06/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.