27INR0190 · BESS · Grimes County
Millsing BESS
Millsing BESS is a 502 MW battery storage project in Grimes County, Texas, connecting at 44645 CNP Singleton 345kV. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 10/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0190
- Capacity
- 502 MW
- Fuel
- BESS (BA)
- Substation
- 44645 CNP Singleton 345kV
- County
- Grimes County
- Interconnecting entity
- Millsing BESS
- Projected COD
- 10/15/2028
- Entered queue
- 02/05/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/08/2024FIS Requested → FIS Approved
- 02/05/2024Entered the queue with 502 MW, projected COD 10/15/2028
- 02/05/2024Screening → FIS Requested