27INR0125 · BESS · Burnet County

RedSun BESS

RedSun BESS is a 84 MW battery storage project in Burnet County, Texas, connecting at Existing Line from Substation Name: Burnet (PSSE#7100) to Substation Name: Bertram (PSSE#7520). ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 08/28/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0125
Capacity
84 MW
Fuel
BESS (BA)
Interconnecting entity
Redsun Solar Project LLC
Projected COD
08/28/2028
Entered queue
11/21/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 07/29/2025
    FIS Requested → FIS Approved
  • 11/21/2023
    Entered the queue with 84 MW, projected COD 08/28/2028
  • 11/21/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.