27INR0124 · Solar · Burnet County

RedSun Solar

RedSun Solar is a 82 MW solar project in Burnet County, Texas, connecting at Tap 138kV 7100 Burnet - 7529 Bertram. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 08/28/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0124
Capacity
82 MW
Fuel
Solar (PV)
Interconnecting entity
Redsun Solar Project LLC
Projected COD
08/28/2028
Entered queue
11/28/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/25/2025
    FIS Approved → IA Signed
  • 07/29/2025
    FIS Requested → FIS Approved
  • 11/28/2023
    Entered the queue with 82 MW, projected COD 08/28/2028
  • 11/28/2023
    Screening → FIS Requested