27INR0076 · Wind · Sterling County
Bob Creek Wind
Bob Creek Wind is a 240 MW wind project in Sterling County, Texas, connecting at 59902 Sand Bluff 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0076
- Capacity
- 240 MW
- Fuel
- Wind (WT)
- Substation
- 59902 Sand Bluff 345kV
- County
- Sterling County
- Interconnecting entity
- NextEra Energy Interconnection Holdings, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 01/09/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Capacity 240 → 240 MW
- 06/06/2025FIS Requested → IA Signed
- 01/09/2024Entered the queue with 240 MW, projected COD 07/01/2028
- 01/09/2024Screening → FIS Requested