27INR0048 · BESS · Nueces County
Sunscape Renewable Energy Storage SLF
Sunscape Renewable Energy Storage SLF is a 0 MW battery storage project in Nueces County, Texas, connecting at Tap 345kV 8455 Lon C Hill -- 80078 Reforzar. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 10/31/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 27INR0048
- Capacity
- 0 MW
- Fuel
- BESS (BA)
- County
- Nueces County
- Interconnecting entity
- Sunscape Renewable Energy LLC
- Projected COD
- 10/31/2028
- Entered queue
- 06/06/2023
- ERCOT zone
- COASTAL
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/18/2024FIS Requested → IA Signed
- 06/06/2023Entered the queue with 0 MW, projected COD 10/31/2028
- 06/06/2023Screening → FIS Requested