26INR0774 · BESS · Austin County
Wallis BESS2
Wallis BESS2 is a 9.9 MW battery storage project in Austin County, Texas, connecting at Wallis. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 02/22/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0774
- Capacity
- 9.9 MW
- Fuel
- BESS (BA)
- Substation
- Wallis
- County
- Austin County
- Interconnecting entity
- Denali Energy Storage LLC
- Projected COD
- 02/22/2027
- Entered queue
- 12/11/2024
- ERCOT zone
- SOUTH
- Size category
- Small
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/11/2024Entered the queue with 9.9 MW, projected COD 02/22/2027
- 12/11/2024Screening → IA Signed
Other projects at this substation
No other projects at this substation.