Wake Wind Energy Repower

COD delayed 1×

Wake Wind Energy Repower is a 252 MW wind project in Crosby County, Texas, connecting at 59904 Cottonwood 345. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 06/04/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0647
Capacity
252 MW
Fuel
Wind (WT)
Interconnecting entity
WAKE WIND ENERGY
Projected COD
06/04/2027
Entered queue
02/28/2014
ERCOT zone
PANHANDLE
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 05/10/2027 → 06/04/2027 (+1 months)
  • 06/16/2026
    FIS Requested → FIS Approved
  • 04/17/2025
    Screening → FIS Requested
  • 02/28/2014
    Entered the queue with 252 MW, projected COD 05/10/2027
  • 02/28/2014
    FIS Approved → IA Signed