26INR0615 · BESS · Bell County
Bell County Morgan Storage
Bell County Morgan Storage is a 256 MW battery storage project in Bell County, Texas, connecting at To Tap 138 kV Trimmier Substation (Bus# 136). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/30/2029.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0615
- Capacity
- 256 MW
- Fuel
- BESS (BA)
- County
- Bell County
- Interconnecting entity
- DM-BCTRM, LLC
- Projected COD
- 12/30/2029
- Entered queue
- 11/14/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/14/2024Entered the queue with 256 MW, projected COD 12/30/2029
- 11/14/2024Screening → FIS Requested