26INR0611 · BESS · Sterling County
Goat Mountain BESS 2
Goat Mountain BESS 2 is a 101 MW battery storage project in Sterling County, Texas, connecting at 76030-Gasconades Creek 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0611
- Capacity
- 101 MW
- Fuel
- BESS (BA)
- Substation
- 76030-Gasconades Creek 345 kV
- County
- Sterling County
- Interconnecting entity
- Clearway Energy Group LLC
- Projected COD
- 06/01/2028
- Entered queue
- 01/17/2025
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/17/2025Entered the queue with 101 MW, projected COD 06/01/2028
- 01/17/2025Screening → FIS Requested
Other projects at this substation
| Goat Mountain BESS | BESS | 201 MW | FIS Requested |