26INR0601 · BESS · Stephens County

Crocus Storage

Crocus Storage is a 51 MW battery storage project in Stephens County, Texas, connecting at Tap 138 kV Gunsolas Creek Sub (1660) – Breckenridge Tap (1613). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0601
Capacity
51 MW
Fuel
BESS (BA)
Interconnecting entity
Crocus Solar, LLC
Projected COD
07/01/2028
Entered queue
01/27/2025
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/01/2026
    FIS Requested → FIS Approved
  • 08/04/2026
    FIS Approved → IA Signed
  • 01/27/2025
    Entered the queue with 51 MW, projected COD 07/01/2028
  • 01/27/2025
    Screening → FIS Requested

Other projects at this substation

Crocus SolarSolar102 MWIA Signed