26INR0597 · Gas · Midland County

Electric E - West Texas Generation 2

Electric E - West Texas Generation 2 is a 0 MW natural gas project in Midland County, Texas, connecting at #18664 SHAWPD 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 09/19/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0597
Capacity
0 MW
Fuel
Gas (GT)
Interconnecting entity
Electric E Power Marketing
Projected COD
09/19/2028
Entered queue
11/06/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 11/06/2024
    Entered the queue with 0 MW, projected COD 09/19/2028
  • 11/06/2024
    Screening → FIS Requested

Other projects at this substation