26INR0577 · BESS · Hopkins County
Pine Forest BESS 2
Withdrawn
Pine Forest BESS 2 is a 201 MW battery storage project in Hopkins County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0577
- Capacity
- 201 MW
- Fuel
- BESS
- Substation
- Not listed
- County
- Hopkins County
- Interconnecting entity
- Not listed
- Projected COD
- n/a
- Entered queue
- 05/21/2025
- ERCOT zone
- n/a
- Size category
- n/a
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/21/2025Listed as inactive