Withdrawn

Signal Hill BESS I is a 123 MW battery storage project in Wichita County, Texas, connecting at 138kV Wichita Falls Cogen (Bus #1498). It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0544
Capacity
123 MW
Fuel
BESS (BA)
Interconnecting entity
Signal Hill Generating LLC
Projected COD
07/31/2030
Entered queue
08/06/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/30/2026
    Listed as inactive
  • 08/06/2024
    Entered the queue with 123 MW, projected COD 07/31/2030
  • 08/06/2024
    Screening → FIS Requested