LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0529 · Gas · Loving County

Electric E - West Texas Generation

Electric E - West Texas Generation is a 44 MW natural gas project in Loving County, Texas, connecting at #11166 ENPOD 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/09/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0529
Capacity
44 MW
Fuel
Gas (GT)
Interconnecting entity
Electric E Power Marketing
Projected COD
04/09/2028
Entered queue
10/10/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/10/2024
    Entered the queue with 44 MW, projected COD 04/09/2028
  • 10/10/2024
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.