26INR0498 · BESS · Parker County
Buckaroo BESS
Buckaroo BESS is a 120 MW battery storage project in Parker County, Texas, connecting at Tap 138kV BROCK(487) – STHBROCKSW(489). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/08/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0498
- Capacity
- 120 MW
- Fuel
- BESS (BA)
- Substation
- Tap 138kV BROCK(487) – STHBROCKSW(489)
- County
- Parker County
- Interconnecting entity
- Weatherford BESS LLC
- Projected COD
- 12/08/2027
- Entered queue
- 05/09/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 11/11/2024Screening → FIS Requested
- 05/09/2024Entered the queue with 120 MW, projected COD 12/08/2027
Other projects at this substation
No other projects at this substation.