26INR0473 · BESS · Scurry County

Canyon BESS SLF

Withdrawn

Canyon BESS SLF is a 0 MW battery storage project in Scurry County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0473
Capacity
0 MW
Fuel
BESS
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
09/25/2025
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/25/2025
    Listed as inactive

Other projects at this substation