26INR0472 · BESS · Wichita County
Bologna BESS
Bologna BESS is a 203 MW battery storage project in Wichita County, Texas, connecting at Tap 138kV #1450 Pleasant Valley Switch - #1492 Wichita Falls Riverbend. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/19/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0472
- Capacity
- 203 MW
- Fuel
- BESS (BA)
- County
- Wichita County
- Interconnecting entity
- MALONEY BESS LLC
- Projected COD
- 04/19/2028
- Entered queue
- 03/20/2024
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/25/2025FIS Requested → FIS Approved
- 03/20/2024Entered the queue with 203 MW, projected COD 04/19/2028
- 03/20/2024Screening → FIS Requested
Other projects at this substation
No other projects at this substation.