26INR0465 · BESS · Bell County
Lavita BESS
Lavita BESS is a 606 MW battery storage project in Bell County, Texas, connecting at Tap 345kV Temple Pecan Creek (3412) - Temple Switch (3414) 345kV ckt 2. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0465
- Capacity
- 606 MW
- Fuel
- BESS (BA)
- County
- Bell County
- Interconnecting entity
- Lavita BESS, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 12/16/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 12/16/2024Entered the queue with 606 MW, projected COD 07/01/2028
- 12/16/2024Screening → FIS Requested