26INR0431 · Solar · Robertson County

Big Rooter West Solar

Big Rooter West Solar is a 403 MW solar project in Robertson County, Texas, connecting at 39950# TNTNP_ONE_3 345 KV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/31/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0431
Capacity
403 MW
Fuel
Solar (PV)
Interconnecting entity
Big Rooter West, LLC
Projected COD
05/31/2028
Entered queue
03/22/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/18/2025
    FIS Requested → IA Signed
  • 03/22/2024
    Entered the queue with 403 MW, projected COD 05/31/2028
  • 03/22/2024
    Screening → FIS Requested

Other projects at this substation

Big Rooter West StorageBESS201 MWFIS Requested