26INR0409 · Solar · Hopkins County
Lucky 7 Solar
Lucky 7 Solar is a 101 MW solar project in Hopkins County, Texas, connecting at Tap 345kV 2621 Sandy Ranch Switch - 2464 CASH SWITCH. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/20/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0409
- Capacity
- 101 MW
- Fuel
- Solar (PV)
- County
- Hopkins County
- Interconnecting entity
- Lucky 7 Solar Farm LLC
- Projected COD
- 09/20/2027
- Entered queue
- 02/29/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/28/2026FIS Requested → FIS Approved
- 08/13/2025FIS Approved → IA Signed
- 02/29/2024Entered the queue with 101 MW, projected COD 09/20/2027
- 02/29/2024Screening → FIS Requested