26INR0370 · Gas · Grimes County

Central Power Station

Central Power Station is a 750 MW natural gas project in Grimes County, Texas, connecting at 967 Gibbons Creek 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0370
Capacity
750 MW
Fuel
Gas (GT)
Interconnecting entity
Hydra-Gen Energy Unlimited
Projected COD
05/01/2027
Entered queue
03/22/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/14/2025
    Screening → FIS Requested
  • 03/22/2024
    Entered the queue with 750 MW, projected COD 05/01/2027

Other projects at this substation

No other projects at this substation.