26INR0370 · Gas · Grimes County
Central Power Station
Central Power Station is a 750 MW natural gas project in Grimes County, Texas, connecting at 967 Gibbons Creek 345kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0370
- Capacity
- 750 MW
- Fuel
- Gas (GT)
- Substation
- 967 Gibbons Creek 345kV
- County
- Grimes County
- Interconnecting entity
- Hydra-Gen Energy Unlimited
- Projected COD
- 05/01/2027
- Entered queue
- 03/22/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 01/14/2025Screening → FIS Requested
- 03/22/2024Entered the queue with 750 MW, projected COD 05/01/2027
Other projects at this substation
No other projects at this substation.