JUNIPERUSSS is a 80 MW solar project in Hopkins County, Texas, connecting at Tap 345kV Cash Switch (bus# 2464) - Sandy Ranch Switch (bus# 2621). ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/09/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0304
Capacity
80 MW
Fuel
Solar (PV)
Interconnecting entity
BLUE STONE RENEWABLE XXI LLC
Projected COD
07/09/2029
Entered queue
01/04/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/04/2024
    Entered the queue with 80 MW, projected COD 07/09/2029
  • 01/04/2024
    Screening → FIS Requested

Other projects at this substation

JUNIPERUS BESSBESS170 MWFIS Requested