26INR0285 · BESS · Grimes County
Hill Valley BESS
Hill Valley BESS is a 246 MW battery storage project in Grimes County, Texas, connecting at 345 kV Singleton (#44645). ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 07/15/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0285
- Capacity
- 246 MW
- Fuel
- BESS (BA)
- Substation
- 345 kV Singleton (#44645)
- County
- Grimes County
- Interconnecting entity
- Hill Valley BESS, LLC
- Projected COD
- 07/15/2028
- Entered queue
- 11/10/2023
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 04/21/2026FIS Approved → IA Signed
- 12/03/2024FIS Requested → FIS Approved
- 11/10/2023Entered the queue with 246 MW, projected COD 07/15/2028
- 11/10/2023Screening → FIS Requested
Other projects at this substation
| Misty Hollow BESS | BESS | 246 MW | IA Signed |